Thursday, June 26, 2008

Day 2 of Directors Cottage Construction...





More progress was made today on the Fritts Directors Cottage. The remaining window frames were created, along with the front door frame. Today, the team also began building the ten trusses which will create the roof of the house.

We are hoping to have a crane lift the trusses into place on Monday morning and to close the house up with OSB (plywood) on Monday afternoon. Then, on Tuesday the windows will be delivered and installed.

1 comment:

John said...

Glad all is going good. Them Razorbacks sure look like they are working hard.

What are the girls doing laying around?

All I see are the guy's